Permit Guide

The Virginia Joint Permit Application for Docks, Explained

The Joint Permit Application is the single form that covers almost all waterfront construction on Virginia’s tidal waters. Instead of filing separately with each agency, you submit one JPA and it gets reviewed concurrently by local, state, and federal authorities. For most Hampton Roads dock and bulkhead projects, this is the permit.

Private dock and bulkhead on a Virginia tidal waterway

Tidewater JPA vs. Standard JPA

The Tidewater JPA is the most commonly used form for typical tidal shoreline projects. Private piers, docks, bulkheads, boat lifts, and living shorelines all go through the Tidewater JPA. The Standard JPA is for more complex work, including dredging and excavation. Most homeowners file the Tidewater version.

What a complete application requires

Applications must be deemed complete before review begins. At minimum you will need project drawings showing materials, installation method, and all dimensions to scale. You will need measurements relative to mean low water showing how far the structure extends channelward. Square footage of any platforms over wetlands or submerged land is required, as are adjacent property owner acknowledgment forms. For projects on waterways under 500 feet wide or inside a cove, owner information from across and around the waterway is also required. CBPA localities require additional documentation.

Incomplete adjacent-owner information is the most common cause of application delay. Getting this right the first time saves weeks.

See What Your Project Will Cost

Get an instant estimate range, then get matched with a licensed local marine contractor. Free, no obligation.

How review works

Since September 1, 2025, the U.S. Army Corps of Engineers is the central point of receipt for all JPAs in Virginia: you file through its online Regulatory Request System, and the application is distributed to your local wetlands board, VMRC’s Habitat Management division, and Virginia DEQ. Before this federal mandate took effect, applications were submitted to VMRC, which served as the clearinghouse. All agencies still review concurrently and independently, and each issues a separate permit or a notice that none is required.

Source: USACE Norfolk District, Notice of Change in Joint Permit Application Submission Process (effective September 1, 2025)

When public hearings are required

Hearings come into play for protested applications, large projects over $500,000 encroaching on state subaqueous land, and projects affecting tidal wetlands or dunes in localities without a local wetlands board. Hearings are held at VMRC’s regular monthly Commission meetings.

Virginia Beach Dock Builders is a free matching and estimating service. We are not a licensed marine contractor. We connect you with independent, licensed marine contractors serving your area. Estimates are informational only; your matched contractor provides the binding quote after a site visit.

The Virginia Joint Permit Application for Docks, Explained — FAQs

Still have questions? Get matched with a local contractor

Estimate My Project & Permit Path

Get an instant estimate range, then get matched with a licensed local marine contractor. Free, no obligation.